Detailed Project Report on tgpc (tetra gold potassium cyanide, 57%)

Detailed Project Report on tgpc (tetra gold potassium cyanide, 57%)

                                                
TGPC
(TETRA GOLD POTASSIUM CYANIDE, 57%)
[CODE NO. 1712]



Tetra Gold Potassium Cyanide KAu(CN)4 is an important chemicals of Gold  Electroplating. For any step of the Gold plating finishing the use of TGPC is a must. This kind of Gold in its salt status is the main core of these chemical treatment and it is necessary to be sure of its purity and content percentage.

The colourless transparent liquid keeps relatively stable acidity. Product is especially free from heterogeneitries formed during its process thereby maintaining high purity.


COST ESTIMATION

Plant Capacity                                    250.00 GM/day            
 Land & Building  (350 Sq.Mtrt)             Rs. 55.00 Lacs
Plant & Machinery                               Rs.4.20 Lacs       
W.C. for 1 Month                                 Rs 86.34  Lacs  
Total Capital Investment                       Rs.1.47  Cr            
Rate of Return                                     44%  
Break Even Point                                35%


INTRODUCTION                                            
USES AND APPLICATION                                        
MARKET SURVEY                                            
PRESENT MANUFACTURERS/SUPPLIERS OF TETRA GOLD POTASSIUM CYANIDE    
RAW MATERIALS                                            
DETAILS OF GOLD COMPOUNDS                                
ELECTRODEPOSITION OF GOLD                                    
STRUCTURE AND TOXICITY OF POTASSIUM CYANIDE                    
MANUFACTURING PROCESS OF TETRA GOLD POTASSIUM CYANIDE            
RAW MATEIALS REQUIREMENTS                                
PROCESS FLOW DIAGRAM                                    
DETAILS OF PROVEN BATH SOLUTION USING TETRA GOLD POTASSIUM CYANIDE    
MATERIAL SAFETY DATA SHEET OF GOLD CHLORIDE                    
STANDARD OPERATING PROCEDURES USING POTASSIUM CYANIDE            
COMPOSITION OF GOLD PLATING BATHS                            
PLANT LAYOUT                                            
PRINCIPLES OF PLANT LAYOUT                                    
PLANT LOCATION FACTORS                                    
EXPLANATION OF TERMS USED IN THE PROJECT REPORT                
SUPPLIERS OF RAW MATERIALS                                
SUPPLIERS OF PLANT & MACHINERIES                            

APPENDIX –A

01.    PLANT ECONOMICS    
02.    LAND & BUILDING     
03.    PLANT AND MACHINERY    
04.    OTHER FIXED ASSESTS    
05.    FIXED CAPITAL    
06.    RAW MATERIAL    
07.    SALARY AND WAGES    
08.    UTILITIES AND OVERHEADS    
09.    TOTAL WORKING CAPITAL    
10.    TOTAL CAPITAL INVESTMENT    
11.    COST OF PRODUCTION    
12.    TURN OVER/ANNUM    
13.    BREAK EVEN POINT     
14.    RESOURCES FOR FINANCE    
15.    INSTALMENT  PAYABLE IN 5 YEARS    
16.    DEPRECIATION CHART FOR 5 YEARS    
17.    PROFIT ANALYSIS FOR 5 YEARS    
18.    PROJECTED BALANCE SHEET FOR (5 YEARS)    
 

Get Free Sample Project Report

Fill in your details to receive a sample industrial project report and explore how our consultancy can help you plan your business professionally.

By submitting this form, you agree to receive communication from our consultancy team regarding industrial project reports and business consultancy services.

Ready to Start Your Industrial Business?

Speak with our experts and get personalized guidance for your manufacturing business idea, project planning, machinery selection, and investment strategy.

Our consultancy team will connect with you to understand your business requirements and guide you on the next steps.